To install small, medium or large cover.
clip image001 002 Acoustic Hoods Installation Step One:
Grasp legs firmly and roll cover into a tight cylinder. Ensure wiring loom is through slot before installation.
  clip image001 003 Acoustic Hoods Installation Step Two:
Keeping a tight grip on the legs, feed the cover through the cut out made for the down lighter.
  clip image001 004 Acoustic Hoods Installation Step Three:
Ensure cover has sprung back into its original cone shape.
(a) Grasp legs and pull down until L section clears the underside of the ceiling.
(b) Move legs out until vertical part of L section normal.is flush with the side of the cut out.
  clip image001 005 Acoustic Hoods Installation Step Four:
Release legs so that they grip the underside of the tile. Remove the excess of both legs. Cut at point A. Once cover is in place, down lighter can be fitted as normal.
To install X-Large or XX-Large Cover.
clip image001 006 Acoustic Hoods Installation Step One: Flatten the cover
clip image001 007 Acoustic Hoods Installation Step Two: Fold the cover into quarters by folding it in half once ….
clip image001 008 Acoustic Hoods Installation ….. and then folding it in half again.
clip image001 010 Acoustic Hoods Installation Step Three: Pass the folded cover through the aperture.
clip image001 011 Acoustic Hoods Installation Step Four: Then fit the down lighter cover as per the manufacture’s instructions – cables may be pushed through the vent slots in the cover.
Check and ensure that there is a distance of 20mm minimum between the down lighter cover and any insulation or acoustic filling in the void.
Remote gearboxes and transformers must be situated outside of the down lighter cover.